Here you will find a select few of the over 350 installations we have installed.
Project: Toronto II
Size: 206.65 kW
Modules: Siliken SLK60P6L 245Wp and 250Wp
Inverters: KACO XP90-H6
Planning period: -
Construction time: 4 weeks |
 |
 |
Project: Mount Brydges
Size: 195.75 kW
Modules: Silfab SLA250M 250Wp
Inverters: Power One
Planning period: -
Construction time: 6 weeks |
 |
 |
Project: Kinghaven
Size:263 kW
Modules: Silfab SLA250M 250Wp
Inverters: Power One PVI-5000-OUTD, PVI-10.0-IOUTD & PVI-12.0-I-OUTD
Planning period: -
Construction time: 12 weeks |
 |
 |
Project: Goderich III
Size: 55.2 kW
Modules: Heliene
Inverters: Power One
Planning period: 8 days
Construction time: 10 days
Permitting period: 16 weeks
Financing: -
Project realization period: 17 weeks |
 |
 |
Project: Kincardine I
Size: 14 kW
Modules: Siliken
Inverters: SMA
Planning period: 1 day
Construction time: 3 days
Permitting period: 14 weeks
Financing: -
Project realization period: 17 weeks |
|
|
Project: Newmarket III
Size: 13 kW
Modules: Heliene
Inverters: Power One
Planning period: 1 day
Construction time: 4 days
Permitting period: 18 weeks
Financing: 6 weeks
Project realization period: 21 weeks |
|
|
Project: Bretten I
Size: 1,100 kW
Modules: Siliken
Inverters: Power One
Planning period: 2 weeks
Construction time: 31 days
Permitting period: 9 weeks
Financing: 6 weeks
Project realization period: 23 weeks |
|
|
Project: Goderich I
Size: 10 kW
Modules: Siliken SLK 60 P6L230
Inverters: SMA SB6000 & SB4000
Planning period: 1 day
Construction time: 4 days
Permitting period: 10 weeks
Financing: N/A
Project realization period: 16 weeks |
|
|
Project: Goderich II
Size: 12 kW Ground-Mounted
Modules: Siliken SLK 60 P6L230
Inverters: SMA SB6000 & SB4000
Planning period: 1 day
Construction time: 4 days
Permitting period: 6 weeks
Financing: 2 weeks
Project realization period: 14 weeks |
|
|
Project: Halle IV
Size: 60 kW
Modules: Canadian Solar
Inverters: SMA
Planning period: 1 week
Construction time: 4 days
Permitting period: 6 weeks
Financing: 2 weeks
Project realization period: 14 weeks |
|
|
Project: 25 Bertal Rd., Toronto
Size: 12 kW
Modules: Suntech
Inverters: SMA
Planning period: 1 week
Construction time: 4 days
Permitting period: 16 weeks
Financing: 1 week
Project realization period (technical evaluation to grid connection): 17 weeks |
|
|
Project: Newmarket I
Size: 10 kW
Modules: Siliken
Inverters: SMA
Planning period: 1 day
Construction time: 4 days (including roof de-icing)
Permitting period: 10 weeks
Financing: N/A
Project realization period (technical evaluation to grid connection): 16 weeks |
|
Project: Solar Valley
Size: 249 kW
Modules: Trina Solar
Inverters: SMA
Planning period: 2 weeks
Construction time: 8 days (including roof de-icing)
Permitting period: 3 weeks
Financing: 4 weeks
Project realization period (technical evaluation to grid connection): 14 weeks |
|
|
Project: Halle
Size: 110 kW
Modules: Canadian Solar
Inverters: SMA
Planning period: 3 weeks
Construction time: 5 days
Permitting period: 9 weeks
Financing: 2 weeks
Project realization period (technical evaluation to grid connection): 16 weeks |
|
|
Project: Saale
Size: 170 kW
Modules: LDK
Inverters: SMA
Planning period: 2 weeks
Construction time: 10 days
Permitting period: 6 weeks
Financing: 2 weeks
Project realization period (technical evaluation to grid connection): 14 weeks |
|
|
Project: Mergentheim
Size: 155 kW
Modules: First Solar & Trina Solar
Inverters: SMA
Planning period: 2 weeks
Construction time: 12 days
Permitting period: 2 weeks
Financing: 3 weeks
Project realization period (technical evaluation to grid connection): 13 weeks |
|
|
Project: Wurzburg
Size: 168 kW
Modules: First Solar
Inverters: Danfoss
Planning period: 3 weeks
Construction time: 19 days
Permitting period: 6 weeks
Financing: 2 weeks
Project realization period (technical evaluation to grid connection): 14 weeks |
|
|
Project: Giebelstadt 1
Size: 205 kW
Modules: BP, FS, Yingli
Inverters: Fronius, Danfoss
Project realization: 16 weeksRight building is an east-west indoor roof with a mounting system; left building is a stable and barn with roof-parallel east-west PV-System
|
|
Projects: Giebelstadt 2
Size: 145 kW
Modules: Sanyo, STP, UniSolar
Inverters: Kaco, SMA, FroniusProject realization: 17 weeksLeft building is a roof parallel system, mounting on north side, and tracking system on back . Right building is a grain storage with mounting systems |
|